Consider two processes P1 and P2, where the periods are p1 = 50 and p2 = 75
and the processing times are t1 = 25 and t2 = 30, respectively. Schedule the
two processes using the following algorithms and illustrate their executions
using Gantt charts.
CPU time periods
P1 25 50
P2 30 75
1.Rate-monotonic scheduling
2.Earliest deadline first
--