作者LadySara (莎拉夫人)
看板P_Management
标题[问题] Risk 的问题
时间Sat May 23 23:06:39 2009
Which of the following is the MOST likely cause of poor risk management ?
A: Inadequate risk response planning.
B: Poor risk monitoring and control.
C: Lack of a prioritized list of risks.
D: Lack of detail in the scope statement.
There is a probability of 0.10 that a given risk will occur in a project.
If it occurs, it will result in a loss of US $10000.
The insurance cost for this event is US $700,
with a deductible amount of US $250.
Should a rational project manager buy this insurance ?
A: Yes, since US $1000 is greater than US $950.
B: Yes, since US $1000 is greater than US $700.
C: No, since the deductible amount changes the expected value of the risk
event.
D: No, since US $1250 is greater than US $ 1000.
这题答案跟我选的不一样,但我脑筋转不出来....
一整个不明白为什麽.....
--
※ 发信站: 批踢踢实业坊(ptt.cc)
◆ From: 123.194.171.53
1F:→ louside:第一题是D 因为PSS是Risk mgmt ITTO里的input 第二题是A똿 05/24 00:46
2F:推 purist:我看不太懂deductible amount的意思..不可能保费700但 05/24 09:01
3F:→ purist:赔偿只有250吧,那是在减免什麽呢...? 05/24 09:01