Question 15:
During the completion of project work, the sponsor asks the project manager
to report on how the project is going. In order to prepare the report, the
project manager asks all the team members what percent complete their work is.
There is one team member who has been hard to manage from the beginning.
In response to being asked what percent complete he is, the team member asks,
"Percent complete of what?" Being tired of such comments, the project
manager reports to the team member's boss that the team member is not
cooperating. Which of the following is likely to be the real problem?
a. The project manager did not get buy-in from the manger for the resources
on the project.
b. The project manager did not create an adequate reward system for team
members to improve their cooperation.
c. The project manager should have had a meeting with the team member's boss
the first time the team member caused trouble.
d. The project manager does not have work packages.
让我简单把故事说一下
你是一个专案的pm
就是在专案进行中时
你的金主问你 "目前工作完成了多少 阿?"
於是你就问所有的team member他们工作进度
唯独其中一人 从一开始就很不合作
没回答你问题不说
还态度不好的回你
"完成什麽工作?"
你很不爽 觉得受够了他
於是把他不合作的情形向他的上司报告
题目就问
造成这情形的真正问题是什麽?
a.在专案人力资源的使用上 PM 并没有得到管理阶层的支持
b. pm没有建立良善的奖励系统使队员更加合作
c. 打从一开始这member有制造麻烦的情形时 pm就该跟他的老板会面
d. PM并没有work package
在pmp考试中 work package = task
也就是 时程和花费已被清楚定义的工作分配
你觉得要选哪一个呢? :)
--
打球别忘找苏菲雅
没有程度但有热度
打欢乐
打欢乐
打欢乐
打欢乐
--
※ 发信站: 批踢踢实业坊(ptt.cc)
◆ From: 220.130.182.222
1F:推 RedTear:应该是D 12/19 21:12
2F:推 birdpon:应该是D 12/19 22:51
3F:推 vbfish:另外补充一点,sponsor指的是PM的主管,因为每个案子一定要先 12/19 23:06
4F:→ vbfish:由主管向各function宣布由谁接PM,这样此PM才开始有舞台的.. 12/19 23:08
5F:→ yule1224:是d 12/20 08:11